Question 109 - PMP discussion

Report
Export

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

A.
Update the project budget with the released team members.
Answers
A.
Update the project budget with the released team members.
B.
Update the restriction log with the new team capacity.
Answers
B.
Update the restriction log with the new team capacity.
C.
Explain the new project requirements to the team.
Answers
C.
Explain the new project requirements to the team.
D.
Explain the new team velocity to the customer.
Answers
D.
Explain the new team velocity to the customer.
Suggested answer: D