Question 110 - PMP discussion
An IT project manager for a project that is 50% complete learns that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?
A.
Require that all team members be physically present for the weekly project review
B.
Offer the team member an incentive to stay until the end of the project
C.
Replace the team member with someone who has similar qualifications and is located closer
D.
Set up a weekly video conference to monitor the progress of the team member's work
Your answer: