List of questions
Related questions
Question 114 - PMP discussion
During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating. As a result, lots of misunderstandings occurred.
What should the project manager do to address this issue?
A.
Check the ground rules of the meeting to review the initial agreement with the team members
B.
Use round-robin check-ins to facilitate the meeting, so all participants have the opportunity to speak
C.
Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates
D.
Identify one team representative to speak up during the daily meeting and share the team updates
Your answer:
0 comments
Sorted by
Leave a comment first