A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?

A.
Established ground rules before the discussion had started
Answers
A.
Established ground rules before the discussion had started
B.
Reinforced that higher-level management has the decision power
Answers
B.
Reinforced that higher-level management has the decision power
C.
Invited a high-level sponsor to the meeting to reduce the level of disagreement
Answers
C.
Invited a high-level sponsor to the meeting to reduce the level of disagreement
D.
Asked stakeholders not to voice their opinions during the meeting
Answers
D.
Asked stakeholders not to voice their opinions during the meeting
Suggested answer: A