A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

A.
Call a meeting with the project team to identify the most appropriate approach
Answers
A.
Call a meeting with the project team to identify the most appropriate approach
B.
Tell the owner that a rough order of magnitude will be provided
Answers
B.
Tell the owner that a rough order of magnitude will be provided
C.
Contact a subject matter expert (SME) for advice and consultation
Answers
C.
Contact a subject matter expert (SME) for advice and consultation
D.
Tell the owner that the task requires more time and expertise
Answers
D.
Tell the owner that the task requires more time and expertise
Suggested answer: B