A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office (PMO) recommends the project manager to lead the next similar project.

What should the project manager do next?

A.
Engage key stakeholders to complete and deliver lessons learned.
Answers
A.
Engage key stakeholders to complete and deliver lessons learned.
B.
Select the same stakeholders for the next project to avoid doing knowledge transfer.
Answers
B.
Select the same stakeholders for the next project to avoid doing knowledge transfer.
C.
Present the project achievements and delegate knowledge transfer to the steering committee.
Answers
C.
Present the project achievements and delegate knowledge transfer to the steering committee.
D.
Request the PMO to manage the lessons learned repository.
Answers
D.
Request the PMO to manage the lessons learned repository.
Suggested answer: A