A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project manager use to manage these risks using an agile approach?

A.
Develop an agile risk matrix to track, assess, and evaluate the uncertainty of the project.
Answers
A.
Develop an agile risk matrix to track, assess, and evaluate the uncertainty of the project.
B.
Implement a scrum risk retrospective to analyze the risks at the end of the project.
Answers
B.
Implement a scrum risk retrospective to analyze the risks at the end of the project.
C.
Assign an agile risk manager to better understand and track the project risks.
Answers
C.
Assign an agile risk manager to better understand and track the project risks.
D.
Evaluate the risks constantly and reprioritize work as the project progresses.
Answers
D.
Evaluate the risks constantly and reprioritize work as the project progresses.
Suggested answer: D