A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.

What should the project manager do?

A.
Ask the product owner to add the missing feature in the backlog.
Answers
A.
Ask the product owner to add the missing feature in the backlog.
B.
Invite stakeholders to discuss the impact of adding the regulatory feature.
Answers
B.
Invite stakeholders to discuss the impact of adding the regulatory feature.
C.
Estimate the related cost and ask for a project extension.
Answers
C.
Estimate the related cost and ask for a project extension.
D.
Increase the capacity of the team to include the missed feature.
Answers
D.
Increase the capacity of the team to include the missed feature.
Suggested answer: B