A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not support.

What should the project manager do next?

A.
Meet with the new project sponsor to review the current project scope and the requested changes.
Answers
A.
Meet with the new project sponsor to review the current project scope and the requested changes.
B.
Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.
Answers
B.
Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.
C.
Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.
Answers
C.
Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.
D.
Inform the new project sponsor that the new aspects will not be included in this project.
Answers
D.
Inform the new project sponsor that the new aspects will not be included in this project.
Suggested answer: A