In an agile team, some of the team members are coming forward to ask for more autonomy on the project.

What should the project manager do in this situation?

A.
Encourage the team lead to make decisions.
Answers
A.
Encourage the team lead to make decisions.
B.
Encourage the team members to make decisions.
Answers
B.
Encourage the team members to make decisions.
C.
Discourage them as conflicts may be created.
Answers
C.
Discourage them as conflicts may be created.
D.
Discourage this request, as it is for the management team.
Answers
D.
Discourage this request, as it is for the management team.
Suggested answer: B