Question 131 - PMP discussion
A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team members. The project sponsor has allocated a monetary award.
How should the project manager utilize the award?
A.
Meet with the team members and ask them how to spend the reward.
B.
Arrange a luncheon for all team members and include team-building sessions.
C.
Draft a points system to allocate a portion of the money for each resource.
D.
Allocate the reward to the team leaders to spend on the team as they see fit.
Your answer: