A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team members. The project sponsor has allocated a monetary award.

How should the project manager utilize the award?

A.
Meet with the team members and ask them how to spend the reward.
Answers
A.
Meet with the team members and ask them how to spend the reward.
B.
Arrange a luncheon for all team members and include team-building sessions.
Answers
B.
Arrange a luncheon for all team members and include team-building sessions.
C.
Draft a points system to allocate a portion of the money for each resource.
Answers
C.
Draft a points system to allocate a portion of the money for each resource.
D.
Allocate the reward to the team leaders to spend on the team as they see fit.
Answers
D.
Allocate the reward to the team leaders to spend on the team as they see fit.
Suggested answer: C