A company is conducting a digital transformation project that has a hard deadline. The marketing team wants to combine this implementation with a new product, and the newly assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are taken into consideration?

A.
Implement a project newsletter so the different team members can be informed about the progress of each project.
Answers
A.
Implement a project newsletter so the different team members can be informed about the progress of each project.
B.
Make sure that each individual project schedule is aligned with the common deadlines.
Answers
B.
Make sure that each individual project schedule is aligned with the common deadlines.
C.
Combine all of the small projects into one big project so the team can collaborate better as one big team.
Answers
C.
Combine all of the small projects into one big project so the team can collaborate better as one big team.
D.
Facilitate communication promoting a Scrum of Scrums so the different teams are aware of the dependencies and progress.
Answers
D.
Facilitate communication promoting a Scrum of Scrums so the different teams are aware of the dependencies and progress.
Suggested answer: D