ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 133 - PMP discussion

Report
Export

During an agile project, a project manager lost one of the resources, and at the same time, uncovered new requirements, which were added to the backlog. What should the project manager do next?

A.
Reevaluate the backlog priority with the product owner since the velocity has been impacted.
Answers
A.
Reevaluate the backlog priority with the product owner since the velocity has been impacted.
B.
Reevaluate the scope of the current iteration to keep the same velocity and timeline.
Answers
B.
Reevaluate the scope of the current iteration to keep the same velocity and timeline.
C.
Reevaluate the velocity as the iteration duration will be impacted by new requirements.
Answers
C.
Reevaluate the velocity as the iteration duration will be impacted by new requirements.
D.
Reevaluate the project schedule as the velocity will be impacted by the loss of resources.
Answers
D.
Reevaluate the project schedule as the velocity will be impacted by the loss of resources.
Suggested answer: A
asked 23/09/2024
Antonio Pombo
30 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first