Question 141 - PMP discussion

Report
Export

During the execution phase of a project, a new department has been created in the company.

The manager of this department has requested to be involved in the regular project communications and reporting cycles.

What should the project manager do?

A.
Ask the project team members to include the manager in all of their communications regarding this project.
Answers
A.
Ask the project team members to include the manager in all of their communications regarding this project.
B.
Inform the manager that only stakeholders identified in the communications management plan should be involved.
Answers
B.
Inform the manager that only stakeholders identified in the communications management plan should be involved.
C.
Perform a stakeholder analysis and update the communications management plan to reflect the new situation.
Answers
C.
Perform a stakeholder analysis and update the communications management plan to reflect the new situation.
D.
Suggest the manager contact the steering committee and project management office (PMO) to be included.
Answers
D.
Suggest the manager contact the steering committee and project management office (PMO) to be included.
Suggested answer: C
asked 23/09/2024
Alvaro Campos
35 questions
User