Question 142 - PMP discussion
Close to the end of a project, a customer claims that some deliverables have not been met and starts initiating change requests.
What should the project manager do next?
A.
Refer to the requirements traceability matrix.
B.
Escalate the change request to the project sponsor.
C.
Revise the project scope baseline.
D.
Review the approved project charter.