ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 142 - PMP discussion

Report
Export

Close to the end of a project, a customer claims that some deliverables have not been met and starts initiating change requests.

What should the project manager do next?

A.
Refer to the requirements traceability matrix.
Answers
A.
Refer to the requirements traceability matrix.
B.
Escalate the change request to the project sponsor.
Answers
B.
Escalate the change request to the project sponsor.
C.
Revise the project scope baseline.
Answers
C.
Revise the project scope baseline.
D.
Review the approved project charter.
Answers
D.
Review the approved project charter.
Suggested answer: A
asked 23/09/2024
Nicoleta Moglan
37 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first