During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that this could be a high risk for the project.

Which action should the project manager take?

A.
Facilitate a supportive level of engagement for this stakeholder.
Answers
A.
Facilitate a supportive level of engagement for this stakeholder.
B.
Ask the project sponsor for advice as it might be possible to work with another stakeholder.
Answers
B.
Ask the project sponsor for advice as it might be possible to work with another stakeholder.
C.
Perform a qualitative risk analysis using a probability and impact matrix.
Answers
C.
Perform a qualitative risk analysis using a probability and impact matrix.
D.
Ensure the key information is accurate and monitor the situation as the project progresses.
Answers
D.
Ensure the key information is accurate and monitor the situation as the project progresses.
Suggested answer: A