Question 152 - PMP discussion
During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that this could be a high risk for the project.
Which action should the project manager take?
A.
Facilitate a supportive level of engagement for this stakeholder.
B.
Ask the project sponsor for advice as it might be possible to work with another stakeholder.
C.
Perform a qualitative risk analysis using a probability and impact matrix.
D.
Ensure the key information is accurate and monitor the situation as the project progresses.