A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was appointed to attend the first meeting with the auditors scheduled for the following week.

What should the project manager do to prepare for the audit?

A.
Reserve story points for the next iteration if needed.
Answers
A.
Reserve story points for the next iteration if needed.
B.
Review the project information.
Answers
B.
Review the project information.
C.
Ask the development team to provide compliance information.
Answers
C.
Ask the development team to provide compliance information.
D.
Ask for a waiver during the audit.
Answers
D.
Ask for a waiver during the audit.
Suggested answer: B