Question 156 - PMP discussion
A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has too many items to allow on-time delivery.
What should the project manager do first?
A.
Update the risk register and present a contingency plan to meet the deadline.
B.
Suggest to the customer to reduce the backlog to meet the date.
C.
Increase the capacity of the team to finish the project on time.
D.
Ask the team to propose a minimum viable product (MVP) to meet the date.