ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 156 - PMP discussion

Report
Export

A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has too many items to allow on-time delivery.

What should the project manager do first?

A.
Update the risk register and present a contingency plan to meet the deadline.
Answers
A.
Update the risk register and present a contingency plan to meet the deadline.
B.
Suggest to the customer to reduce the backlog to meet the date.
Answers
B.
Suggest to the customer to reduce the backlog to meet the date.
C.
Increase the capacity of the team to finish the project on time.
Answers
C.
Increase the capacity of the team to finish the project on time.
D.
Ask the team to propose a minimum viable product (MVP) to meet the date.
Answers
D.
Ask the team to propose a minimum viable product (MVP) to meet the date.
Suggested answer: D
asked 23/09/2024
Stašo Zver
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first