A project manager is working on a complex project with a high degree of change.
What strategy should the project manager use to ensure a successful project completion?
A.
Update the project management plan to reduce the possibility of scope creep.
B.
Schedule a regular risk review with the project management team.
C.
Increase the active engagement and participation of key stakeholders.
D.
Create a project change roadmap to keep track of all unforeseen changes.