A healthcare company is in the process of deploying an innovative healthcare solution globally.

The project team has completed a limited release. The stakeholders have raised concerns about global healthcare guidelines and risks.

What should the project manager do next?

A.
Evaluate lessons learned from similar projects prior to deployment.
Answers
A.
Evaluate lessons learned from similar projects prior to deployment.
B.
Perform a qualitative risk analysis on the identified project risks.
Answers
B.
Perform a qualitative risk analysis on the identified project risks.
C.
Review compliance and regulatory requirements with stakeholders.
Answers
C.
Review compliance and regulatory requirements with stakeholders.
D.
Conduct a feasibility analysis of deploying the solution globally.
Answers
D.
Conduct a feasibility analysis of deploying the solution globally.
Suggested answer: C