List of questions
Related questions
Question 165 - PMP discussion
A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they feel it is a waste of time.
What should the project manager do?
A.
Welcome and involve the contractors as part of the project team.
B.
Ask the contractors to meet with the customer independently.
C.
Ask the customer to develop a document with the requirements.
D.
Warn and penalize the contractors who do not attend the meeting.
Your answer:
0 comments
Sorted by
Leave a comment first