ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 166 - PMP discussion

Report
Export

A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects, and there is no capacity for any developer to take on additional work.

What should the project manager do next to fulfill this resource need?

A.
Determine resource allocation options based on project priority.
Answers
A.
Determine resource allocation options based on project priority.
B.
Apply changes to the existing resource allocations and inform the development manager.
Answers
B.
Apply changes to the existing resource allocations and inform the development manager.
C.
Meet with the sponsor to determine how to rebaseline the schedule.
Answers
C.
Meet with the sponsor to determine how to rebaseline the schedule.
D.
Inform the sponsor of the situation and request an extension of the target completion date.
Answers
D.
Inform the sponsor of the situation and request an extension of the target completion date.
Suggested answer: A
asked 23/09/2024
Louis Flink
43 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first