Question 174 - PMP discussion
A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.
What should the project manager do?
A.
Refer to the configuration management knowledge base for similar projects delivered in the past.
B.
Arrange for a workshop with the customer to understand the business values expected from the outcomes.
C.
Include a representative from the customer to work collaboratively with the team.
D.
Acknowledge that the current team needs improvement and hire more qualified team members.