Question 175 - PMP discussion
A project manager is managing a project with team members who are working all over the globe.
The project manager notices that each team member's deliverables do not meet the requirements.
What should the project manager do first?
A.
Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables are submitted.
B.
Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.
C.
Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework the deliverables.
D.
Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.