Question 178 - PMP discussion
A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.
How should the project manager support their claim to the vendor?
A.
Provide the failed test results along with the agreed-upon acceptance criteria.
B.
Share unsuccessful results from previous projects with a similar scope.
C.
Document in the risk log that the issues in the system were already identified.
D.
Show that the acceptance criteria were changed by the vendor without approval.
Your answer: