A project manager agreed to a team member's request to have an alternative working schedule whereby they begin working at 12:00 p.m. each day. This arrangement has worked well for the project, but has recently been scrutinized by members from other project teams because the company's core working hours begin at 9:00 a.m.

What should the project manager have done to prevent this situation?

A.
Broken down the situation to identify the root cause
Answers
A.
Broken down the situation to identify the root cause
B.
Determined communication methods and channels
Answers
B.
Determined communication methods and channels
C.
Analyzed the boundaries of the negotiations for agreement
Answers
C.
Analyzed the boundaries of the negotiations for agreement
D.
Managed and rectified the ground rule violations
Answers
D.
Managed and rectified the ground rule violations
Suggested answer: C