A project manager is working on a financial system implementation project for a government company. One of the key stakeholders, who uses predictive approaches, does not like virtual tools such as chats, task trackers, and so forth. They prefer email, telephone calls, and face-to- face meetings.

How should the project manager approach this situation?

A.
Use regular screen-sharing sessions to show the progress to the stakeholder.
Answers
A.
Use regular screen-sharing sessions to show the progress to the stakeholder.
B.
Align and agree with the stakeholder on the communication approach.
Answers
B.
Align and agree with the stakeholder on the communication approach.
C.
Ask the manager to use virtual communication tools and online dashboards.
Answers
C.
Ask the manager to use virtual communication tools and online dashboards.
D.
Create a digital dashboard to meet the manager's information needs.
Answers
D.
Create a digital dashboard to meet the manager's information needs.
Suggested answer: B