Question 196 - PMP discussion
A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project manager knows this team member could add value to the project.
What should the project manager do to get the most value from this team member?
A.
Advise the team member not to share personal information from past projects with the entire team.
B.
Consult with the project sponsor to find out if it is allowed to share personal information with the entire team.
C.
Advise the team member to focus on the current project and consider the past conflicts as lessons learned.
D.
Consult with human resources (HR) and check company policies on what is allowed to advise the team member.
Your answer: