A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project.

What should the project manager do in this situation?

A.
Delegate other team members to complete this team member's tasks.
Answers
A.
Delegate other team members to complete this team member's tasks.
B.
Mentor the team member and provide the necessary training.
Answers
B.
Mentor the team member and provide the necessary training.
C.
Request the team member to move to another team.
Answers
C.
Request the team member to move to another team.
D.
Include the team member in an improvement program through a human resources (HR) request.
Answers
D.
Include the team member in an improvement program through a human resources (HR) request.
Suggested answer: B