Question 200 - PMP discussion

Report
Export

A project manager is managing a project that requires specialized architecture services. This project was identified as a high risk for the organization. The project manager works with an external architect who is highly specialized. However, the architect will soon resign because they accepted an offer from another firm.

What should the project manager do next?

A.
Discuss this with the project team, assess the impact, and decide on the appropriate actions to follow.
Answers
A.
Discuss this with the project team, assess the impact, and decide on the appropriate actions to follow.
B.
Ask the architect for the contact details for their new employer and call their account manager.
Answers
B.
Ask the architect for the contact details for their new employer and call their account manager.
C.
Call the account manager and ask them to retain the expert by offering them an incentive.
Answers
C.
Call the account manager and ask them to retain the expert by offering them an incentive.
D.
Escalate the issue to the procurement department and ask them to discuss this with the vendor firm.
Answers
D.
Escalate the issue to the procurement department and ask them to discuss this with the vendor firm.
Suggested answer: A
asked 23/09/2024
Kurt Onal
30 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first