Question 202 - PMP discussion
A new engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the project manager before acting.
What should the project manager do?
A.
Obtain related training for the new team member.
B.
Determine the appropriate level of decision-making authority and empower the engineer.
C.
Make all of the decisions for the engineer in order to keep the workflow on track.
D.
Replace the resource with an experienced engineer.