A senior project manager has included a junior project manager as part of the project team.

During a coaching session, the junior project manager asks the senior project manager how to be efficient and reduce rework.

How should the senior project manager respond?

A.
Use a work breakdown structure (WBS) to create a project schedule based on the project and resource requirements.
Answers
A.
Use a work breakdown structure (WBS) to create a project schedule based on the project and resource requirements.
B.
Monitor resource allocation to ensure that team members work 8 hours per day.
Answers
B.
Monitor resource allocation to ensure that team members work 8 hours per day.
C.
Assign project tasks to the team regardless of their skills to accomplish the project schedule.
Answers
C.
Assign project tasks to the team regardless of their skills to accomplish the project schedule.
D.
Schedule daily meetings with key stakeholders to assess the effectiveness of the project management plan.
Answers
D.
Schedule daily meetings with key stakeholders to assess the effectiveness of the project management plan.
Suggested answer: A