PMI PMP Practice Test - Questions Answers, Page 21
List of questions
Question 201

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the appropriate stakeholder participation and involvement level required for successful project delivery.
What should the project manager do?
Question 202

A new engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the project manager before acting.
What should the project manager do?
Question 203

A senior project manager has included a junior project manager as part of the project team.
During a coaching session, the junior project manager asks the senior project manager how to be efficient and reduce rework.
How should the senior project manager respond?
Question 204

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now.
What should the project manager do to mitigate this risk?
Explanation:
To mitigate the risk of the team not feeling confident about the product increment, the project manager should schedule an additional interim demo with the product owner. This will give the team an opportunity to validate their work with the product owner and receive feedback early in the sprint. This feedback can then be incorporated into the work before the end of the sprint, which can improve the quality of the product increment and increase the team's confidence in it.
Additionally, it's important for the project manager to communicate the need for an additional demo with the stakeholders and to make sure that the team has enough time to incorporate the feedback into their work.
Explanation:
Question 205

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.
This is going to significantly impact the deliverable.
What should the project manager do?
Question 206

A project lead is working on an agile project to build the team's vision, including the decision- making process. It was decided that the team will vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team makes a decision that the project lead strongly disagrees with.
How should the project lead proceed?
Question 207

A project manager is newly appointed to lead a project team that will be working remotely. The project manager decided to use a set of tools that worked well for previous projects. However, a few team members are not happy with this plan.
What should the project manager have done to avoid this?
Question 208

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant.
What should the project manager do next?
Question 209

A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts with the other team members. As a result, the other team members are refusing to work with the developer. Since the developer is a high performer, the project goals may be negatively impacted if they leave the team.
What should the project manager do in this situation?
Question 210

A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has been working on this project for 6 months, and the morale of the team is low due to the schedule.
What can the project manager do to motivate the team?
Question