Question 206 - PMP discussion
A project lead is working on an agile project to build the team's vision, including the decision- making process. It was decided that the team will vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team makes a decision that the project lead strongly disagrees with.
How should the project lead proceed?
A.
Refuse to let the team proceed with the work based on their decision.
B.
Take the technical team lead aside and try to persuade them to change their vote.
C.
Note the reasons for the disagreement and let the team proceed.
D.
Set up a meeting with the project champion and ask them to intervene.