An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.
This is going to significantly impact the deliverable.
What should the project manager do?
A.
Request additional funding from the sponsor to obtain a new resource to fill in the gap.
B.
Inform the customer of the impact immediately and prepare for escalation.
C.
Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.
D.
Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.