A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has been working on this project for 6 months, and the morale of the team is low due to the schedule.

What can the project manager do to motivate the team?

A.
Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.
Answers
A.
Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.
B.
Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.
Answers
B.
Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.
C.
Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.
Answers
C.
Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.
D.
Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.
Answers
D.
Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.
Suggested answer: D