Question 211 - PMP discussion
A project manager starts to receive emails from different stakeholders requesting information about the project status.
What should the project manager do to avoid this in the future?
A.
Schedule weekly project status meetings with all stakeholders including the customer and internal resources.
B.
Include the project stakeholders' needs while planning the project communications strategy.
C.
Designate a team member to respond to the emails from these stakeholders.
D.
Include the stakeholders' emails in all of the project status communications.
Your answer: