A project is starting its second iteration out of six. During the daily meeting, a team member asks for help. In order to finish a deliverable, an approval from the design department will be needed.

What should the project manager do?

A.
Meet with the design manager to ask for the necessary approval.
Answers
A.
Meet with the design manager to ask for the necessary approval.
B.
Invite a design team member to the next daily meeting.
Answers
B.
Invite a design team member to the next daily meeting.
C.
Update the issue log and escalate it to the project sponsor.
Answers
C.
Update the issue log and escalate it to the project sponsor.
D.
Replace this iteration deliverable for one without any blockers.
Answers
D.
Replace this iteration deliverable for one without any blockers.
Suggested answer: A