A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the year. The project team is concerned that one of those tickets could be the winner.

What should the project manager do first?

A.
Reassure the sponsor by explaining the probability of this risk materializing is extremely low.
Answers
A.
Reassure the sponsor by explaining the probability of this risk materializing is extremely low.
B.
Carry out tests to verify that the system does not fail again due to the high occurrence of events.
Answers
B.
Carry out tests to verify that the system does not fail again due to the high occurrence of events.
C.
Review the list of risks to verify that this issue was considered and execute the detailed action plan.
Answers
C.
Review the list of risks to verify that this issue was considered and execute the detailed action plan.
D.
Inform the sponsor about the issue and make a request for sufficient funds to be made available.
Answers
D.
Inform the sponsor about the issue and make a request for sufficient funds to be made available.
Suggested answer: C