Question 219 - PMP discussion

Report
Export

A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization and asks the project manager to pay attention to changes that can affect the project.

Which action should the project manager take to identify changes that may affect the product?

A.
Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.
Answers
A.
Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.
B.
Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.
Answers
B.
Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.
C.
Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.
Answers
C.
Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.
D.
Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.
Answers
D.
Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.
Suggested answer: C