Question 221 - PMP discussion
In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager found out that the delay is due to the developer's lack of understanding of the customer requirements shared by the off-site team.
What should the project manager do?
A.
Replace the developer with a skilled resource.
B.
Perform a root cause analysis (RCA) with the team members.
C.
Facilitate communication to ensure clarification of the requirements.
D.
Conduct frequent performance reviews.