ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 222 - PMP discussion

Report
Export

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?

A.
Ensure that the schedule is aligned with the vision and objectives.
Answers
A.
Ensure that the schedule is aligned with the vision and objectives.
B.
Escalate the compliance issue to the project management office (PMO).
Answers
B.
Escalate the compliance issue to the project management office (PMO).
C.
Congratulate the team and move on to the execution phase.
Answers
C.
Congratulate the team and move on to the execution phase.
D.
Develop a new detailed schedule with the team and project sponsor.
Answers
D.
Develop a new detailed schedule with the team and project sponsor.
Suggested answer: A
asked 23/09/2024
Eli Thompson
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first