A project manager is assigned to a technical research project. The project team has already been assigned, and the main subject matter expert (SME) sends the project manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

A.
Discuss the list with the project sponsor to confirm that the resources have the required skills.
Answers
A.
Discuss the list with the project sponsor to confirm that the resources have the required skills.
B.
Ask the functional manager to review the resource pool and recommend the right individuals to join the team.
Answers
B.
Ask the functional manager to review the resource pool and recommend the right individuals to join the team.
C.
Meet with the project team to understand their skills and identify potential gaps and training requirements.
Answers
C.
Meet with the project team to understand their skills and identify potential gaps and training requirements.
D.
Send the list to the project team and ask them to get training on the required skills.
Answers
D.
Send the list to the project team and ask them to get training on the required skills.
Suggested answer: C