A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

A.
Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.
Answers
A.
Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.
B.
Sequence the tasks with estimates and add standard risk reserves to use for software development.
Answers
B.
Sequence the tasks with estimates and add standard risk reserves to use for software development.
C.
Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.
Answers
C.
Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.
D.
Work with the team to understand their views and add the appropriate dependencies and risks.
Answers
D.
Work with the team to understand their views and add the appropriate dependencies and risks.
Suggested answer: D

Explanation:

You can't provide a prototype, at least a good one without consulting with the team first or even having any work done. The selected answer seems like the PM is doing everything without even talking with the team, and that's a recipe for failure.