ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 230 - PMP discussion

Report
Export

According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?

A.
The product owner should not ask the team to change their sprint commitments.
Answers
A.
The product owner should not ask the team to change their sprint commitments.
B.
The team is accepting too much work in the sprint after it has started.
Answers
B.
The team is accepting too much work in the sprint after it has started.
C.
The team is not meeting the expectations of the product owner.
Answers
C.
The team is not meeting the expectations of the product owner.
D.
The team should have stopped on day 4 and started a new sprint.
Answers
D.
The team should have stopped on day 4 and started a new sprint.
Suggested answer: B
asked 23/09/2024
Matteo Zamori
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first