According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?
A.
The product owner should not ask the team to change their sprint commitments.
B.
The team is accepting too much work in the sprint after it has started.
C.
The team is not meeting the expectations of the product owner.
D.
The team should have stopped on day 4 and started a new sprint.