Question 231 - PMP discussion
After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security.
During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.
What should the project manager do?
A.
Continue the iteration and add the requested changes.
B.
Continue the iteration and review the change with the customer.
C.
Cancel the iteration and meet with the product owner.
D.
Cancel the iteration and add the requested changes.