Question 237 - PMP discussion
A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.
What should the project manager do next?
A.
Review the change control process to ensure quality management artifacts are updated as part of the change.
B.
Review the quality management process and perform a process audit as part of ongoing quality assurance.
C.
Review the communications management plan to ensure change requests are communicated to the affected team members.
D.
Review the quality management process with the project management office (PMO) to ensure compliance with best practices.