Question 238 - PMP discussion
A project manager has been assigned with initiating a large project to deliver complex equipment.
Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.
Which approach should the project manager choose for this project?
A.
Adaptive
B.
Hybrid
C.
Predictive
D.
Agile