A project manager has been assigned with initiating a large project to deliver complex equipment.

Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.

Which approach should the project manager choose for this project?

A.
Adaptive
Answers
A.
Adaptive
B.
Hybrid
Answers
B.
Hybrid
C.
Predictive
Answers
C.
Predictive
D.
Agile
Answers
D.
Agile
Suggested answer: B