List of questions
Related questions
Question 240 - PMP discussion
A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.
What should the project manager do next?
A.
Discuss extending the mass production timeline by 3 months with the project sponsor.
B.
Assess and evaluate the certification process and understand the best and worst case scenarios.
C.
Engage a consultant to shorten the certification process to meet the schedule requirement.
D.
Meet with senior management to discuss the possibility of an extension to the project timeline.
Your answer:
0 comments
Sorted by
Leave a comment first