Question 241 - PMP discussion
In the middle of the execution phase for a big project, a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress.
What should the project manager do first?
A.
Inform the client about the change.
B.
Update the risk register with a new risk.
C.
Present the project to the stakeholder.
D.
Revise the project schedule.